I've been working with Friends of Park Hill Park to try and secure an update on the latest position on the Water Tower works.
We've had below from officers which I hope will be of interest:
"
Subject: RE: Water tower renovations
Hello Cllr Appleton,
I touched base with my colleague from the capital delivery team and she updated with the below summary points.
· Whilst installing the scaffolding within the tower it became evident that a redesign of the final scaffolding layout was needed, causing some delay.
· Scaffolding is currently 80% complete and it’s expected to be done within the month.
· Once done, the steel worker/ specialist will be able to inspect, take measurements and then finalise the design and build of the required components.
· At this stage we can’t be sure how long this last phase will take, and then when we near completion, but we will update you when we have a clearer timeframe.
I hope that is in part helpful. We’ll of course be in touch again."